The Nightingales: First of the bathrooms arrive

Another busy week at The Nightingales in Welford-on-Avon; Bathroom suites arrive for Plot One and Plot Three gets her windows…

There was a crispness to the air this week and we were grateful most of the work was indoors (apart from Matt and Bob that is, who gallantly volunteered to do the fencing – it’s ok, we left them with a small fire to keep them  warm).

  • Plot One
    Bathrooms and Ensuites are being fitted, and kitchen is now floored and has a handsome Quartz worksurface (viewings, by appointment only – will be available shortly)
  • Plot Two
    A first coat of paint now graces the first floor. Downstairs, doors are being hung and hinged.
  • Plot Three
    Handsome window frames now complement the stonework and the internal vacuum pipework is installed

Our progress so far…