Wind in The Willows…

As gale force winds battered our site this week, we give great thanks to our team who have managed to pull this build right back on to schedule after the big freeze during January.

With roof, windows and doors now on, we can proceed whatever the weather!

All walls are now finished. Kitchens are going in. Stairs and doors should be done by next week.

Take a look.